Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
G1 Penetrante Sud
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 964
Project
Name: G1 Pénétrante Sud
Investments: EIB
Client: MINISTERE DE L'EQUIPEMENT,DE L'AMENAGEMENT DU TERRITOIRE
Support: Loans
Country: Tunisia
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2022/20
Date Filed: Oct. 11, 2022
Date Closed: Nov. 13, 2023
Status: Closed With Outputs
Description
Complaint Stages
Filing
Oct. 11, 2022
Filing
Status:
Start Date: Oct. 11, 2022
Registration
Oct. 11, 2022 -
Dec. 14, 2022
Registration
Status: Closed With Output
Start Date: Oct. 11, 2022
End Date: Dec. 14, 2022
Eligibility
Dec. 14, 2022 -
May 11, 2023
Eligibility
Status: Closed With Output
Start Date: Dec. 14, 2022
End Date: May 11, 2023
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Complaint not yet reached stage, Eligibility in progress
Compliance Review
May 11, 2023 -
Nov. 9, 2023
Compliance Review
Status: Closed With Output
Explanation: Complaint not yet reached stage, Eligibility in progress
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Complaint not yet reached stage, Eligibility in progress
Closed
Nov. 13, 2023
Timeline
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
G1 Penetrante Sud | EIB CM | Tunisia | 16/08/2022 | Closed With Outputs Outside Process |