Programa de Mejoramiento de Barrios II (PROMEBA II) | Accountability Console
Complaints IAMs Register Login

Loading...

Programa de Mejoramiento de Barrios II (PROMEBA II)

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 495

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 191

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 865

Browse Complaints

Land reform

Description: Project relates to development of or changes to legal frameworks regarding land tenure.

Complaints in this Sector: 27

Browse Complaints

Project

Name: Programa de Mejoramiento de Barrios II (PROMEBA II)

Investments: IDB

Client:

Support: Loans

Country: Argentina

Complaint

IAM: Independent Consultation and Investigation Mechanism (MICI)

ID: MICI-AR-2010-009

Date Filed: Nov. 24, 2010

Date Closed: April 4, 2011

Status: Closed With Outputs Outside Process

Description

The Request presented to the ICIM, presents the concerns of FundaciĆ³n Hugo Gauna, the organization responsible for all public works in the area of the Project, about the negative impact that the construction of access roads would have in the area of the botanical garden that houses a building where since 2002, several activities targeted for more than 70 children and youth at risk including educational, religious, touristic and other related to social assistant are being conducted. The Request indicates that the Requester was not consulted at any stage of the Project.

Complaint Stages

Filing

Nov. 24, 2010

Filing

Status:

Start Date: Nov. 24, 2010

Registration

Nov. 24, 2010 -

Dec. 2, 2010

Registration

Status: Closed With Output

Start Date: Nov. 24, 2010

End Date: Dec. 2, 2010

Eligibility

Dec. 2, 2010 -

March 10, 2011

Eligibility

Status: Closed With Output

Explanation: Addressed outside process, Management is addressing or has addressed concerns

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Addressed outside process, Matter resolved outside of mechanism

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Addressed outside process, Matter resolved outside mechanism

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

April 4, 2011

Timeline

Involved Groups

Name Complaints Group Type
FundaciĆ³n Hugo Gauna 1 Local CSO