Zenata Urban Development Project
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 359
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 482
Sectors
Community capacity and development
Description: Project relates to programs targeted at training, capacity-building, and/or enabling public participation for specific groups within the community.
Complaints in this Sector: 113
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 964
Project
Name: Zenata Urban Development Project
Investments: EIB
Client: SOCIETE D'AMENAGEMENT ZENATA
Support: Loans
Country: Morocco
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2022/08
Date Filed: April 28, 2022
Date Closed: April 5, 2023
Status: Closed With Outputs
Description
Complaint Stages
Filing
April 28, 2022
Filing
Status:
Start Date: April 28, 2022
Registration
April 28, 2022 -
May 2, 2022
Registration
Status: Closed With Output
Start Date: April 28, 2022
End Date: May 2, 2022
Eligibility
May 2, 2022 -
Oct. 12, 2022
Eligibility
Status: Closed With Output
Start Date: May 2, 2022
End Date: Oct. 12, 2022
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Complaint not yet reached stage, Dispute Resolution in progress
Compliance Review
Oct. 12, 2022 -
March 24, 2023
Compliance Review
Status: Closed With Output
Start Date: Oct. 12, 2022
End Date: March 24, 2023
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Complaint not yet reached stage, Dispute Resolution in progress
Closed
April 5, 2023
Timeline
Related Complaints