Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.
4 Results
Showing Only Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit (Show All Results)
Top Results By:
-
Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit
...requesting IDA Nov. 4, 1994 materials/documents cited by the Request 1o. Materials/documents received from Management Nov. 9, 1994 Nov. 15. 1994 11. Fax sent to the Requesters requesting evidence Nov. 21, 1994 Requested urgent response. indication that the two requesters who asked for anonymity had taken steps to resolve their problems with Bank management or any other ...
WB Inspection Panel - Nepal - 1994 -
Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit
Eligibility: Inspection Panel Report and Recommendation
...Request “[Ilf the Request appears to contain sufficient required information...”. While recognizing that there were deficiencies in the formalities, in accordance with this para, the Chairman, on L November 3, 1994, registered the Request in the Panel Register; notified the Requester, the Executive Directors and the President of IDA of the registration; and transmitted to the President a copy of the original Request together with faxed copies of the attachments and evidence of re...
WB Inspection Panel - Nepal - 1994 -
Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit
Management Response: Management Response (English)
...Requester dated July 7, 1 9 9 4 requested documentation. T h e response, dated July 18, 1 9 9 4 , referred t h e Requester t o the Project Information Center in Kathmandu, which h o u s e s all the requested documentation. We also enclosed a list of t h e documentation available a t t h e World Bank’s Public Information Center (PIC) in Washington. A second letter from the Requester dated October 7, 1 9 9 4 requested ...
WB Inspection Panel - Nepal - 1994 -
Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit
Compliance Report: Investigation Report (English)
...requested that the Bank provide additional funding. By February 1987, all reports indicated no progress. 5. A review by the Bank in May 1987 was rather more concerned about the project as a whole: NEA’s compliance with the agreements reached in prior reviews was described as “extremely poor.” This was followed by a statement in July 1987 to the Bank that “the above consultants would not be asked to develop a resettlement action plan, as the project does not envisage the resettlement of per...