Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

1228 Results

Top Results By:

Show All

  1. Complaint > Visayas Base-Load Power Project

    Compliance Report: CRP Final Report [PDF] (Management Response and Requester Response to CRP Draft Report are attached)

    ...Requesters’ Representatives Mr. Aaron Pedrosa, Jr., Secretary General, Freedom from Debt Coalition Cebu (FDCC) Engr. Vicente Obando, Requester / Requesters’ Representative Nongovernment Agencies Ms. Frannie Aliganga – Women Sector Leader Ms. Gloria Ramos – Global Legal Action on Climate Change (GLACC) Atty. Benjamin Cabrido – Philippine Earth Justice Center, Inc. (PEJC) Mr. Vince Cinches – Cebu Alliance for Renewable Energy (CARE) Attachment 1 27 Response from the Requesters 28 Attachm...

    ADB Special Project Facilitator and Compliance Review Panel - Philippines - 2012
  2. Complaint > Ecodevelopment Project

    Registration: 11-Notice of Registration (English)

    ...REQUEST RQ98/l April 3, 1998 NOTICE OF REGISTRATION Dear Sir: Re: Requestfor Inspection -India: Ecodevelopment Project (Loan No. 29160-IN) (GEF Trust Fund Grant Number TF028479 IN) The Inspection Panel (the "Panel") received a Request for Inspection (the "Request") dated March 10, 1998 on April3, 1998 fro...

    WB Inspection Panel - India - 1998
  3. Complaint > Rondonia Natural Resources Management Project

    Timeline: Register

    ...Request for Inspection received by Secretariat June 16, 1995 2. Request Registered June 19, 1995 3. Notice of Registration with the Request sent to the June 19, 1995 President 4. Notice of Registration sent to: 5. Requesters 6. Executive Directors June 19, 1995 7. Notice ofRegistration put on Internet PIC [hand delivered] to beforwarded to Tokyo, London & Paris WB...

    WB Inspection Panel - Brazil - 1995
  4. Complaint > Governance Promotion Adjustment Loan

    Management Response: 25-Management Response (English)

    ...Request for Inspection, IPN Request RQ 01/4 (hereafter referred to as “the Request”), concerning the Governance Promotion Adjustment Loan (GPAL), entered into between The Independent State of Papua New Guinea (“The Borrower”) and IBRD (“The Bank”). II. THE REQUEST 2. The Request for Inspection to the Bank’s Inspection Panel was submitted by the Centre for Environmental Law and Community Rights, Inc. (CELCOR), located in Papua New Guinea, which ...

    WB Inspection Panel - Papua New Guinea - 2001
  5. Complaint > Nenskra Hydropower Project

    Filing: Request for Compliance Review

    ...requests for publishing the contract , including public hearings at the 27 April and 22 August, where representatives of the Non Governmental organizations as well as local communities directly request contract transparency for the public. The company and the government representatives refused without any justification. Given the fact that the project cost is very high, more than 1 billion US dollars, and that it represents public-private project, we believe that it is necessary to ensure pu...

    ADB Special Project Facilitator and Compliance Review Panel - Georgia - 2017
  6. Complaint > Multitranche Financing Facility Road Network Development Program

    Filing: Complaint

    ...request you to help local people to address their concerns before road construction starts and resettlement plan will be implemented without violating ADB policies and requirements. Complain letter from APs is attached. Please, we request you not to disclose the names of complainers per their request due to their fear of intimidation and harassment from the executing agencies. Looking forward to hear from you soon, Mirvari Gahramanly Oil worker’s rights protection organization Petitio...

    ADB Special Project Facilitator and Compliance Review Panel - Azerbaijan - 2009
  7. Complaint > Santiago-Valparaiso-Viña Toll Road Guarantee

    Registration: Notice of Registration

    ...Request MICI-BID-CH-2016-0102 referring to the operation REFERENCE: “Santiago-Valparaiso-Viña Toll Road Guarantee” (CH0167) DATE: May 27, 2016 Request for Supplemental Information to the Request and RE: determination of the maximum deadline for its submission to the MICI Dear Sirs, We have reviewed your Request and the information contained therein, and we have determined that certain information is...

    IDB Independent Consultation and Investigation Mechanism - Chile - 2016
  8. Complaint > Kozloduy International Decommissioning Support Fund

    Eligibility: Eligibility Assessment Report

    ...president of ARC NGO Craiova in relation with the Kozloduy International Decommissioning Support Fund (KIDSF) 1 The Complaint was submitted by a number of civil society representatives from Craiova, Romania alleging impacts by the activities of the Kozloduy International Decommissioning Support Fund administered by the EBRD. The Complaint requested that a Problem-solving Initiative and a Compliance Review be und...

    EBRD Independent Project Accountability Mechanism - Bulgaria
  9. Complaint > Northern Corridor Highway Improvement Program - Santa Barbara - Rurrenabaque and San Buenaventura

    Filing: Request received by Executive Secretariat

    ...Request and appendixes. We also request that you keep us informed of any developments or progress hereof. We are also available to provide any information or clarification that may be deemed necessary to proceed with this request. Looking forward to a reply hereon, I remain sincerely yours, FOBOMADE ICIM Note: Due to confidentiality requirements from the Requesters, this document has been edited. Translation from the Original Request in Spanish. ICIM Re...

    IDB Independent Consultation and Investigation Mechanism - Bolivia - 2011
  10. Complaint > Natural Resource Management Project

    Management Action Plan: 84-First Management Progress Report (English)

    ...Requesters”). 2. The Executive Directors and the President of IDA were notified by the Panel of receipt of the Request. Management responded to the claims in the Request on March 15, 2013. In its Eligibility Report to the Board, the Panel found the Request eligible, and recommended that the Executive Directors authorize an investigation. The investigation was authorized by the Executive Directors on June 7, 2013. 3. On June 28, 2013 the Panel received a second Request submitted ...

    WB Inspection Panel - Kenya - 2013
  11. Complaint > Dinant-01/CAO Vice President Request

    Appraisal: CAO Appraisal for Audit of IFC: Corporacion Dinant S.A. de C.V., Honduras - Case of Appraisal initiated by CAO Vice President, August 13, 2012

    ...President Summary This appraisal relates to IFC’s investment in Corporación Dinant, a vertically-integrated integrated palm oil and food company in Honduras.. In this instance a CAO’s compliance appraisal was initiated by the CAO Vice President in response to a letter submitted to the President of the World Bank Group in November 2010 and conversations between CAO and ...

    IFC Compliance Advisor/Ombudsman - Honduras - 2012
  12. Complaint > Power Development Project

    Registration: 87-Notice of Registration (English)

    ...Request for Inspection Nepal: Power Development Project (P043311) Receipt of Request On July 10, 2013, the Inspection Panel received a Request for Inspection (hereafter "the Request") related to the Nepal: Power Development Project (PDP, "the Project"), and specifically its 220 kV Khimti-Dhalkebar Transmission Line (KDTL) under its Component C. The Requesters The Request was submitted...

    WB Inspection Panel - Nepal - 2013
  13. Complaint > Rondonia Natural Resources Management Project

    Management Action Plan: Management Progress Report

    ...Request In the case of this Request, communities previously adversely affected in Rondônia by the POLONOROESTE program expected beneficial effects from the implementation of PLANAFLORO according to the standards and timetable promised by the Bank, but expectations were not met. Therefore, on June 14, 1995, the intended beneficiaries represented by local non governmental organizations (“NGOs”) requested the Panel to investigate (“Request for Inspection”) the reasons ...

    WB Inspection Panel - Brazil - 1995
  14. Complaint > None

    Policy Document: Operating Procedures

    ...Request is not the same as a previous Request on which the Panel has already made a recommendation. If the Request raises similar matters as a previous Request, then the new Request must present new evidence or circumstances not known at the time of the prior request related to the Requesters’ concerns. 31. On the basis of this review, within 15 business days of receipt of the Request, the Panel decides whether: (a) to ask for additional information from Requesters; (b) to issue a Notice of...

    - - 2022
  15. Complaint > Termoelectrica del Golfo Project

    Eligibility: Issuance of Eligibility Memorandum

    ...Request filed by Ernesto Márquez Torres, Samuel Celio Martínez, and Efraín Pozos Adrián, representing the Council of Ejido [cooperative farm] Las Palmas, municipality of Tamuín, in the state of San Luis Potosí, México (hereinafter the Requesters). 1.2. The Request follows up on an earlier submission to ICIM’s predecessor mechanism, alleging harm due to IDB’s failure to adequately supervise the design and implementation of the Project. The Request alleges that ...

    IDB Independent Consultation and Investigation Mechanism - Mexico - 2011
  16. Complaint > West African Gas Pipeline Project

    Eligibility: 40-Eligibility Report Final (English)

    ...Request for Inspection Re: Request for Inspection GHANA: West African Gas Pipeline Project (IDA Guarantee No. B-006-0-GH) Inspection Panel Recommendation 1. On April 27, 2006, the Inspection Panel received a Request for Inspection related to the West African Gas Pipeline Project1 . The Request was submitted by the Ifesowapo Host Communities Forum of the Wes...

    WB Inspection Panel - Ghana, Nigeria - 2006
  17. Complaint > Land Reform and Poverty Alleviation Project, 2nd Request

    Registration: 18-Notice of Registration (English)

    ...Request. Although the Second Request contains substantially the same allegations about failures in the project’s design and implementation and possible violations of Bank policies and procedures, the Requesters claim that the Second Request is justified by new circumstances and new evidence not known by and/or available to the Requesters at the time of the prior Request.3 The Requesters claim that they now have evidence, inter alia, th...

    WB Inspection Panel - Brazil - 1999
  18. Complaint > Special Structural Adjustment Loan

    Registration: 17-Notice of Registration (English)

    ...Request for Inspection in Spanish dated July 20, 1999 related to the above referenced loan (“the Loan”) and on August 9, 1999 an acceptable translation thereof. Also, at the request of the Chairman of the Panel, the Requesters submitted some clarifications to the statements made in the original request on August 11, 1999 (both the original request and clarifications hereinafter referred to as “the Request”). The Request was submitted by a group of attorneys of the Centro de Estudi...

    WB Inspection Panel - Argentina - 1999
  19. Complaint > Phase 1B of Lesotho Highlands Water Project, 1st Request

    Registration: 12-Notice of Registration (English)

    ...Requesters in this case wish to remain anonymous and so ask the Panel to keep their names confidential. In this instance the Panel did not receive the Request and cover letter in the sealed envelope delivered by the Requesters. The cover letter indicates that the the World Bank staff in Pretoria have obtained the names of the Requesters. It appears that the Editors of a South African newspaper which published a letter by the Requesters are aware of the Requesters identity. The Panel nevertheless...

    WB Inspection Panel - Lesotho - 1998
  20. Complaint > Mumbai Urban Transport Project

    Compliance Review: 32-Investigation Report (English)

    ...Request (The “Fourth Request”): On December 23, 2004, the Panel received another Request for Inspection (the “Fourth Request”) dated December 4, 2004, related to the same Project. Unlike the first three Requests that focused on issues related to the SCLR, the fourth Request addressed the JVLR. On December 29, 2004, the Panel notified the Executive Directors, the President and Management that it had received the Fourth Request. This Fourth Request ...

    WB Inspection Panel - India - 2004