Bujagali Energy-08/Bujagali

Issues

Labor

Description: Complaint raises concerns about violations of appropriate labor standards related to the project, including issues regarding compensation, workplace conditions, retaliation, and child or forced labor.

Complaints with this Issue: 95

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 325

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 865

Browse Complaints

Project

Name: Bujagali Energy Ltd

Investments: IFC 6732, IFC 24408

Client: Bujagali Energy, World Power Holdings

Support: Loans, Risk Guarantee

Country: Uganda

Complaint

IAM: Compliance Advisor/Ombudsman (CAO)

ID: uganda-bujagali-energy-08bujagali

Date Filed: June 6, 2017

Status: Monitoring

Description

The complaint was submitted to CAO in June 2017 by a former employee of the former construction contractor, Salini Costruttori. The complainant claims that in 2009, during the time he was employed at the project site he suffered an injury that caused him severe chronic backache, for which he has not received any compensation. CAO’s compliance appraisal found the Bujagali Energy-08 complaint to be similar in substance to a March 2011 complaint (Bujagali Energy-04) from workers who were injured while working on the construction of the project for the same Engineering, Procurement & Construction (EPC) contractor. The earlier case led to a CAO compliance investigation (also concerning the Bujagali Energy-06 case) that was publicly released in December 2017. Considering that CAO already looked into IFC’s analysis of the worker’s compensation structure and safety supervision during its investigation related to the Bujagali Energy-04 and Bujagali Energy-06 complaints, CAO determined that no investigation on this matter is merited at this time and decided to merge this case with the Bujagali Energy-04 and Bujagali Energy-06 cases for the purpose of monitoring.

Complaint Stages

Filing

June 6, 2017

Filing

Status:

Start Date: June 6, 2017

Registration

Not Undertaken

Registration

Status: Not Undertaken

Explanation: Not offered by mechanism, Stage is not practiced by mechanism

Eligibility

June 6, 2017 -

April 12, 2018

Eligibility

Status: Closed With Output

Start Date: June 6, 2017

End Date: April 12, 2018

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Actor(s) involved refused to participate, Company or government refused to go through dispute resolution

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Other

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

April 12, 2018

Monitoring

Status: In Progress

Explanation: Case closed in earlier stage

Closed

Not Closed