Gibe III Hydropower Plant

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 526

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 343

Browse Complaints

Project

Name: Gilgel Gibe 3

Investments: EIB

Client:

Support: Loans

Country: Ethiopia

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/A/2010/01

Date Filed: June 8, 2010

Date Closed: May 10, 2011

Status: Closed With Outputs

Description

Complaint On 8 June 2010, Campagna per la Riforma della Banca Mondiale lodged a complaint with the EIB Complaints Mechanism (EIB-CM) whereby the lack of transparency by the EIB in the Gibe III Hydropower Plant project was alleged. In their view, the EIB would have – by means of Technical Assistance financed in the pre-appraisal stage – carried out a “shadow appraisal” which did not allow any stakeholders’ engagement. EIB-CM Action The inquiry of the EIB-CM, besides exploring the extensive correspondence between the parties on the matter, focused on the assessment of the constraints of confidentiality of the claimed information as well as the compliance of the stakeholders’ engagement performed by the EIB competent services with the EIB standards and practices. Conclusions and Recommendations The EIB-CM concluded that the EIB was not carrying out a “shadow” appraisal, but decided to engage additional and extraordinary financial resources as Technical Assistance to improve the quality of the project impact assessments at a preliminary stage, given the global scrutiny of the project as well as the lessons learnt in the previous hydropower plant projects financed in Ethiopia. Due to this additional engagement materialising in an Independent Review of the ESIA carried out by the promoter and given the great complexity of the issues affecting the project under consideration, the EIB-CM considered that the EIB operational services should have accepted the complainant’s request for an additional meeting after the EIB Management Committee had formally authorised the provision of financial assistance to the promoter and recommended that, when the activity performed by the EIB services during the pre-appraisal of a proposed operation exceeds the preliminary basic screening to be carried out during this phase of the project cycle (as in case of financial support to the assessment of the project provided within the framework of Technical Assistance), the EIB shall modulate its stakeholders’ engagement taking into consideration the financial and human resources deployed in the additional assessment with a view to complying with its standards and practices. As regards the requests for access to project-related information, the EIB CM recommended that – in the absence of arguments for the confidentiality of the Terms of Reference for the EFTA study - the EIB competent services should reconsider the possibility of the partial (if not total) disclosure of such a document.

Complaint Stages

Filing

June 8, 2010

Filing

Status:

Start Date: June 8, 2010

Registration

June 8, 2010 -

June 8, 2010

Registration

Status: Closed With Output

Start Date: June 8, 2010

End Date: June 8, 2010

Eligibility

June 8, 2010 -

Aug. 24, 2010

Eligibility

Status: Closed With Output

Start Date: June 8, 2010

End Date: Aug. 24, 2010

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary

Compliance Review

Aug. 24, 2010 -

April 20, 2011

Compliance Review

Status: Closed With Output

Start Date: Aug. 24, 2010

End Date: April 20, 2011

Has Compliance Report: No

Non-Compliance Found: Yes

Monitoring

May 9, 2011 -

May 9, 2011

Monitoring

Status: Closed With Output

Start Date: May 9, 2011

End Date: May 9, 2011

Closed

May 10, 2011

Timeline

Documents

Name Category Description
Compliance Review Compliance Report