IPP4 Al-Manakher Power Project | Accountability Console
Complaints IAMs Register Login

Loading...

IPP4 Al-Manakher Power Project

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 359

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 525

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Indigenous peoples

Description: Complaint raises concerns about impacts on indigenous or traditional communities.

Complaints with this Issue: 88

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 342

Browse Complaints

Project

Name: IPP4 Al-Manakher Power Project

Investments: EBRD

Client:

Support: Loans

Country: Jordan

Complaint

IAM: Project Complaint Mechanism (PCM)

ID: 2015/02

Date Filed: Aug. 3, 2015

Date Closed: Jan. 4, 2017

Status: Closed With Outputs

Complaint Stages

Filing

Aug. 3, 2015

Filing

Status:

Start Date: Aug. 3, 2015

Registration

Aug. 3, 2015 -

Aug. 11, 2015

Registration

Status: Closed With Output

Start Date: Aug. 3, 2015

End Date: Aug. 11, 2015

Eligibility

Aug. 11, 2015 -

Jan. 8, 2016

Eligibility

Status: Closed With Output

Start Date: Aug. 11, 2015

End Date: Jan. 8, 2016

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Actor(s) involved refused to participate, Company or government refused to go through dispute resolution

Compliance Review

Jan. 18, 2016 -

Jan. 4, 2017

Compliance Review

Status: Closed With Output

Start Date: Jan. 18, 2016

End Date: Jan. 4, 2017

Has Compliance Report: Yes

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

Jan. 4, 2017

Timeline