Route E420 Frasnes-Bruly RTE | Accountability Console
Complaints IAMs Register Login

Loading...

Route E420 Frasnes-Bruly RTE

Issues

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 482

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 965

Browse Complaints

Project

Name: Route E420 Frasnes-Bruly RTE

Investments: EIB

Client:

Support: Loans

Country: Belgium

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2014/02

Date Filed: Jan. 22, 2014

Date Closed: Dec. 19, 2018

Status: Closed With Outputs

Description

n January 2014, the EIB's Complaints Mechanism (EIB-CM) received a complaint from an individual. The complaint concerns the motorway section between Frasnes-lez-Couvin and Brûly on route E420 in Belgium. The complaint consists of three allegations concerning the project, which is financed by the EIB. The allegations concern the following: effectiveness of the project, studied alternatives and environmental impact.

Complaint Stages

Filing

Jan. 22, 2014

Filing

Status:

Start Date: Jan. 22, 2014

Registration

Jan. 22, 2014 -

Jan. 22, 2014

Registration

Status: Closed With Output

Start Date: Jan. 22, 2014

End Date: Jan. 22, 2014

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Start Date: None

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Start Date: None

Compliance Review

Jan. 22, 2014 -

Dec. 13, 2018

Compliance Review

Status: Closed Without Output

Start Date: Jan. 22, 2014

End Date: Dec. 13, 2018

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Start Date: None

Closed

Dec. 19, 2018

Timeline