Teresina Enhancing Municipal Governance and Quality of Life Project and its Additional Financing | Accountability Console
Complaints IAMs Register Login

Loading...

Teresina Enhancing Municipal Governance and Quality of Life Project and its Additional Financing

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 495

Browse Complaints

Cultural heritage

Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.

Complaints with this Issue: 113

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 440

Browse Complaints

Sectors

Conservation and environmental protection

Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.

Complaints in this Sector: 61

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 865

Browse Complaints

Complaint

IAM: Inspection Panel (Panel)

ID: 140

Date Filed: Aug. 23, 2019

Date Closed: Jan. 11, 2023

Status: Closed With Outputs

Description

On August 23, 2019, the Panel received a Request for Inspection of the project from 202 families who live in the Afonso Mafrense and São Joaquim neighborhoods of Teresina, Piauí, Brazil. While the Requesters are supportive of the project, they oppose their resettlement and claim there are other possible project designs that would enable them to stay in their current location. They contend that community members have been living in this location for several decades and the project will cause cultural, social and economic harm. They also raise concerns about lack of consultation with affected communities and disclosure of information.

Complaint Stages

Filing

Aug. 23, 2019

Filing

Status:

Start Date: Aug. 23, 2019

Registration

Aug. 23, 2019 -

Sept. 19, 2019

Registration

Status: Closed With Output

Start Date: Aug. 23, 2019

End Date: Sept. 19, 2019

Eligibility

Oct. 22, 2019 -

Dec. 13, 2019

Eligibility

Status: Closed With Output

Start Date: Oct. 22, 2019

End Date: Dec. 13, 2019

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not offered by mechanism, Stage is not practiced by mechanism

Compliance Review

Jan. 7, 2020 -

July 22, 2020

Compliance Review

Status: Closed With Output

Start Date: Jan. 7, 2020

End Date: July 22, 2020

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

Sept. 30, 2020 -

Jan. 11, 2023

Monitoring

Status: Closed With Output

Start Date: Sept. 30, 2020

End Date: Jan. 11, 2023

Closed

Jan. 11, 2023

Timeline