Mining Infrastructure Investment Support and Mining Infrastructure Support - Additional Financing

Issues

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 344

Browse Complaints

Water

Description: Complaint raises concerns about access to or availability of water. Concerns related to water pollution are not included.

Complaints with this Issue: 194

Browse Complaints

Sectors

Extractives (oil, gas, mining)

Description: Project relates to the extractive industries, including oil, gas, and mining. Examples may include mines, drilling operations, pipelines, and the associated legal frameworks.

Complaints in this Sector: 199

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 169

Browse Complaints

Project

Name: Mining Infrastructure Investment Support

Investments: WB P145439

Client:

Support:

Country: Mongolia

Complaint

IAM: Inspection Panel (Panel)

ID: 125

Date Filed: April 2, 2018

Date Closed: Aug. 6, 2018

Status: Closed Without Outputs

Description

On April 2, 2018, the Inspection Panel received three Requests for Inspection related to the Mongolia Mining Infrastructure Investment Support Project and its Additional Financing (MINIS). A second Request was submitted by Oyu Tolgoi Watch and 27 residents of Gurvantes in South Gobi region who asked for confidentiality. They claimed potential harm from water management plans and the establishment of the Altain-Uvur Gobiin River Basin Administration financed by the project. Specific harms alleged include loss of access to traditional land and water sources, environmental impacts, and lack of consultation and disclosure of information.

Complaint Stages

Filing

April 2, 2018

Filing

Status:

Start Date: April 2, 2018

Registration

April 2, 2018 -

May 11, 2018

Registration

Status: Closed With Output

Start Date: April 2, 2018

End Date: May 11, 2018

Eligibility

July 1, 2018 -

Aug. 6, 2018

Eligibility

Status: Closed With Output

Explanation: Mechanism deemed involvement unnecessary; Addressed outside process, Management is addressing or has addressed concerns

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not offered by mechanism, Stage is not practiced by mechanism

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Aug. 6, 2018

Timeline