Nyamagasami 2 HPP Limited

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 551

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 509

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 357

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 363

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 1030

Browse Complaints

Project

Name: Nyamagasani 2 HPP Limited

Investments: FMO 51478

Client: Nyamagasani 2 HPP Limited

Support: Loans

Country: Uganda

Complaint

IAM: Independent Complaints Mechanism (ICM)

ID: 20-003

Date Filed: July 6, 2020

Date Closed: July 31, 2024

Status: Closed With Outputs

Description

The complaint concerns issues of resettlement and damages to properties caused by the project’s construction activities. The complainants argue that their properties were damaged or rendered unsuitable for living due to the construction of the FMO-financed project and that, nonetheless, adequate compensation or appropriate replacement housing were not delivered despite earlier commitments made by the client company. In particular, the complainants contend that: (1) As a result of the construction activities, 13 houses remain located at a steep edge of the constructed canal in areas that present significant risk for the residents’ lives, and should thus be replaced by houses in safe locations. Furthermore, the complainants argue that guard rails and fences offered by the client company as protection do not satisfy the need for safe housing. (2) In relation to replacement houses that were provided by the client company for relocated persons, the complainants assert that the project failed to install kitchens and latrines. Instead, the property owners were given a sum of 2,000,000 Ugandan shilling, which is insufficient to properly construct these fixtures. (3) Eight of the complainants assert that they suffered damages to their land or crops due to the construction works during the years of 2017, 2018 and 2019, and were not compensated adequately for these damages. (4) Two of the complainants claim that due to the construction activities their land became “orphaned”, i.e. of no value, and thus should be acquired from them, in line with the commitments made by the client company. The complainants therefore seek appropriate compensation and replacement housing in relation to damages they suffered due to the construction activities of the project. (Source doc: Second Admissibility Notice, '2020-March | Notice of Admissability Case no 2020-03 Nyamagasani 2 HPP')

Complaint Stages

Filing

July 6, 2020

Filing

Status:

Start Date: July 6, 2020

Registration

July 6, 2020 -

July 6, 2020

Registration

Status: Closed With Output

Start Date: July 6, 2020

End Date: July 6, 2020

Eligibility

July 6, 2020 -

July 27, 2020

Eligibility

Status: Closed With Output

Start Date: July 6, 2020

End Date: July 27, 2020

Dispute Resolution

June 1, 2021 -

March 31, 2022

Dispute Resolution

Status: Closed With Output

Start Date: June 1, 2021

End Date: March 31, 2022

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint settled in Dispute Resolution so Compliance Review not offered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

March 31, 2022 -

July 31, 2024

Monitoring

Status: Closed With Output

Start Date: March 31, 2022

End Date: July 31, 2024

Closed

July 31, 2024

Timeline

Related Complaints